AI Risk Engine

Stanmore Road Cohousing Ā· Daily digest as at 2026-06-04

Each risk is a real detectable condition — not a static list. Risk levels derive from the same compliance matrix as the dashboard.

PS1 (structural fire) response overdue

critical

RFI-2026-0035 issued 2026-05-22, due 2026-06-06. No response received. National median response 11.0 days (MBIE Jun 2025). Now 11 days overdue.

Action: Escalate to structural engineer. Confirm CPEng on Auckland Council PS Register.

FC-14 fire rating contradicted across documents

critical

Fire Report Rev C §4.3 specifies -/60/60; Drawing A-310 Rev C shows -/30/30. Detected by revision diff engine (Drawing Rev C→D).

Action: Fire engineer must issue errata or drawing revision. Do not submit response to RFI-2026-0041 without resolution.

Drawing Rev D: 3 new penetrations not in fire penetration schedule

high

Drawing Rev D (2026-05-09) added 3 service penetrations at Level 2. Fire penetration schedule FP-001 has not been updated.

Action: Update FP-001 before RFI response to RFI-2026-0039.

2 open RFIs approaching 15-day mark

high

RFI-2026-0039 and RFI-2026-0041 clock-stopped since 2026-05-27 and 2026-05-29 respectively. Each day of delay extends total elapsed time beyond the 17-day national median (MBIE Q4 2025).

Action: Prioritise mechanical drawing update (RFI-2026-0039) and FC-14 resolution (RFI-2026-0041).

PS1 fire design author not confirmed on AC PS Register

medium

Auckland Council AC2301 requires PS1 authors to be on the Auckland Council Producer Statement Register. Confirmation not yet on file.

Action: Confirm CPEng registration status before PS1 is submitted.